3/22-3/28

Throughout this week, some adjustments where done to the bogie. The bottom wheel which prevent the bogie from rotating an undesirable angle were welded in place. The previous test showed that the wheels were placed in the wrong spot thus we needed to placed them further up. Also, once the whole bogie was welded and all adjustments were done, all parts were powder coated to prevent any corrosions. Currently, both bogies are powder coated. The steering will be place on the bogie as soon as a complicated shaft for the gear box is completed. The parts arrived within two days as previously mentioned thus we will be testing the bogie and steering on the track as soon as possible.